§ 15.5. TIMELINESS OF UPDATE SUBMITTAL FOR TAP PLAN APPLICATIONS
(A)
An applicant shall file a formal update with the City of Austin in compliance with the timelines set forth below or the application shall be considered inactive:
1.
Update one shall be filed no later than the 30th business day after the final case comment report is issued by the City.
2.
Update two shall be filed no later than the 20th business day after the final case comment report is issued by the City in response to update one.
3.
Update three shall be filed no later than the 15th business day after the final case comment report is issued by the City in response to update two.
4.
All subsequent updates shall be filed no later than the 15th business day after the final case comment report is issued by the City in response to the previous update.
(B)
The director of Austin Water may alter the deadlines in (A) based on good cause.
(C)
Projects deemed inactive shall pay a reactivation fee prior to continuing the processing of the application.