§ 15.7. REVIEW TIMES  


Latest version.
  • Review Schedule in business days for review processes within the Land Development Code.

    Review times for applications and processes Business days after application
    Title 25-1 General Requirements and Procedures
     Development Assessment review [25-1-62] 15
    Title 25 Subdivisions
      Preliminary Plan review [25-4-56(C)] 20
      Plat review [25-4-82(B)] 18
      Notification of plat determination [25-4-82(C)] 20
     Notification of plat determination update [25-4-82(E)] 10
    Title 25 Site Plans
      Notification of site plan determination [25-5-114(A)(1)] 20
      Notification of small project site plan determination [25-5-114(A)(2)] 7
      Notification of site plan update determination [25-5-114(A)(3)] 10
      Site Plan Review Report 25-5-143(A) 18
      Site Plan Review Report Notification 25-5-143(B) 20
     Site Plan Review of initial update to meet Commission-imposed conditions 25-5-148(B) 10
    25-11-63 Building, Demo, and Relocation Permit Review periods
      Type of Permit
      1) Commercial buildings, new construction 25
      2) Commercial buildings, remodeling and finishouts 15
      3) Residential, new construction 15
      4) Residential, remodeling of a complying structure 5
      5a) Residential, remodeling of a noncomplying structure 5
      5b) Residential, additions to a noncomplying structure 15
      6) Sign, other than a nonconforming off-premise sign 10
      7) Replacement of nonconforming off-premise sign 10
      8) Repair of nonconforming off-premise sign 10
      9) Demolition 5
     10) Relocation 5

     

Source: Rule No. R161-16.10 , 6-6-16; Rule No. R161-17.11 , 5-15-17.