§ 1.20.0. WATER AND WASTEWATER SUBDIVISION SUBMITTAL
1)
Basic.
a)
All water and/or wastewater plans will include the following: Engineer's signature, engineer's seal, date, north direction, scale and general location sketch. Engineer's construction notes will be in compliance with standard City practices and specifications. Subdivision file number will also be required.
b)
Include all permit numbers such as waterway development, highway permit, railroad permit, etc.
c)
Include volume and page of all easements. Show location of easement, size and location of main within easement.
d)
Show and give information on lots, lot numbers, block numbers, street name, property line dimension, right of way dimension, curb basis and sidewalk locations.
e)
Give highway stations where mains are within or crossing state highways.
2)
Water Plan View.
a)
This will include location and size of existing water mains, existing wastewater mains, all other utilities, proposed water mains, proposed wastewater mains, proposed water services, proposed valves, proposed fire hydrants and proposed water appurtenances.
b)
For mains of 12 inches and larger give the following: station numbers for starting point, ending point, point of intersections, point of curvature, point of tangency, fire hydrant locations, drain fire hydrant locations and air release valve locations.
3)
Wastewater Plan View. This will include location and size of existing wastewater mains, existing water mains, all other utilities, proposed wastewater mains, proposed wastewater services and proposed manhole locations. Include station numbers for starting point, ending point, manhole, point of curvature, point of tangency, point of intersection, top of finish grade elevation at manholes and bottom of subgrade elevation on profile.
4)
Required Permits. The following are examples of permits, permissions and letters that may be required prior to approval:
a)
Final plat recording, street grade approval, Waterway Development Permit.
b)
Highway Permit.
c)
Railroad Permit.
d)
Gas Company Permission.
e)
Easement.
f)
Williamson County Approval.
g)
Travis County Approval.
h)
Water District Approval.
i)
Municipal Utility District Approval.
j)
Texas Health Department Approval.
k)
Non-occupancy Letter.
l)
Council approval of approach main, variance approval of approach main and subsequent user fee.
m)
Other permits, permissions.
n)
Letters not listed above may be required at the discretion of the Austin Water Utility Pipeline Engineering Division. Approval and/or acceptance must be given for permits, permissions or letters prior to final approval of plans for construction.
o)
Hays County Approval.