§ 4.6.2.5.1. Framing Inspection Prerequisites:
Latest version.
a)
All trade work and Stage 1 Energy Code required sealing (Foam) must be completed prior
to scheduling this inspection, and
b)
The electrical rough inspection must be approved or conducted with minimal violations
prior to scheduling the Framing Inspection.