§ 14-11-101. APPLICABILITY; DIRECTOR; PERMIT REQUIRED.
(A)
This article does not apply to city-owned utilities.
(B)
In this division, "director" means the department director designated by the city manager.
(C)
Unless a person obtains a permit from the director under this article or demonstrates to the director that the person is exempt from obtaining a permit for use or occupation of public right-of-way, a person may not perform any activity in the public right-of-way that includes:
(1)
construction;
(2)
excavation;
(3)
installation, maintenance, or placement of facilities intended for short or long-term occupancy of the public right-of-way; or
(4)
temporary use.
(D)
A person claiming an exemption from permitting under this article must request and obtain a written exemption determination from the director 30 days prior to commencing any activity in the right-of-way by providing the director evidence in a form determined by the director necessary to make a determination that the person is exempt.
Source: Ord. No. 20170817-045 , Pt. 2, 8-17-17.