§ 15-3-38. CROSS CONNECTION SURVEY REQUIRED.  


Latest version.
  • (A)

    This section applies if an applicant intends to use water withdrawn from a fire hydrant as potable water.

    (B)

    Before the director may issue a permit, the director shall:

    (1)

    conduct a cross connection survey as provided in Section 15-1-16 ( Cross-Connection Survey ); and

    (2)

    conduct a cross connection survey of the applicant's potable water facilities, equipment, and appurtenances.

    (C)

    The applicant shall pay the amount prescribed by separate ordinance for the cross connection surveys.

Source: Ord. 20051020-005.