§ 25-12-267. EXPIRATION.  


Latest version.
  • Except as provided in Section 25-12-268 ( Extension ) and Section 25-12-269 ( Reactivation ), a permit expires on the 181st day:

    1.

    after the date that the permit is issued, if the project has received no inspections as required under this Code; or

    2.

    after the date of the last scheduled inspection if that inspection is scheduled before the 181st day and once performed, shows progress towards completion of the project.

Source: Ord. 20100624-143.