§ 25-13-81. PERMIT REQUIRED.  


Latest version.
  • (A)

    Except as provided in Subsection (B), a person must obtain a permit under this chapter from the director before the person may:

    (1)

    construct a new structure;

    (2)

    substantially change or repair an existing structure;

    (3)

    establish a new use, or substantially change an existing use;

    (4)

    replace, rebuild, or substantially change or repair a nonconforming structure;

    (5)

    replace, substantially change, allow to grow higher, or replant a nonconforming object of natural growth.

    (B)

    A permit under this chapter is not required for a structure or object of natural growth that:

    (1)

    is not more than 75 feet in height above the natural ground level;

    (2)

    does not exceed the height limits of Section 25-13-22 (Height Limits); and

    (3)

    is permitted under Section 25-13-42 (Land Uses).

Source: Ord. 010809-78; Ord. 031211-11.