§ 30-1-371. ACCEPTANCE BY THE CITY OR COUNTY.
(A)
The single office shall schedule a final acceptance meeting at the site and shall invite the:
(1)
consulting engineer;
(2)
contractors, as appropriate;
(3)
affected utilities; and
(4)
appropriate staff;
(B)
The single office may not issue a final acceptance letter until:
(1)
work identified in the accountable official's report has been completed;
(2)
the following items have been submitted:
(a)
construction summary report;
(b)
consulting engineer's concurrence letter;
(c)
reproducible plans, certified "as built" by the consulting engineer;
(d)
if required, one-year warranty bonds;
(e)
cash or cashier's check for balances due, if any; and
(3)
if the owner executed a developer contract, the conditions of the contract have been satisfied.
(C)
The single office shall issue an acceptance letter to an owner who meets the requirements of Subsection (B). If the owner has not satisfied all requirements, the single office shall issue a list of requirements that the owner must satisfy.
Source: City Code Section 25-1-314; Ord. 031211-11; Ord. 031211-42.