§ 25-1-394. COPY OF RIGHT-OF-WAY USE PERMIT TO BE KEPT ON-SITE.


Latest version.
  • (A)

    A permit holder shall keep a copy of the right of way use permit in an accessible place on the construction site or business premises during the period for which the permit is valid.

    (B)

    A permit must state the name of the site manager, supervisor, project superintendent, or prime contractor to be contacted by the inspector or police officer if problems exist.

    (C)

    A permit holder's failure to produce a copy of the permit on request from a police officer, an authorized representative of the City, or a City building inspector, is prima facie evidence that a permit does not exist.

Source: Section 13-1-71(b); Ord. 990225-70; Ord. 031211-11; Ord. 20060504-039.