§ 25-5-43. SITE PLAN RELEASE.  


Latest version.
  • (A)

    The director may release a site plan after:

    (1)

    the site plan is approved;

    (2)

    the applicant posts the required fiscal security with the director;

    (3)

    the time period for filing an appeal of the approval expires, or each interested party signs and submits to the director a written waiver of the right to appeal; and

    (4)

    if applicable, tenant notification has been provided for the period required under Section 25-1-712 ( Tenant Notification Required ).

    (B)

    Except as provided in Subsection (C), the director's release of a site plan authorizes the applicant to develop the site in accordance with the site plan.

    (C)

    An applicant may not begin development of site plan improvements that require a building permit until a building permit is issued. The building official may not issue a building permit until the director releases a site plan.

Source: Section 13-1-606; Ord. 990225-70; Ord. 000309-39; Ord. 031211-11; Ord. No. 20160901-050 , Pt. 8, 9-12-16.