Austin |
Land Development Code |
Title 25. LAND DEVELOPMENT. |
Chapter 25-5. SITE PLANS. |
Article 3. LAND USE COMMISSION APPROVED SITE PLANS. |
§ 25-5-147. ACTION BY THE LAND USE COMMISSION.
(A)
The Land Use Commission shall act on a site plan application not later than the 14th day after it closes the public hearing.
(B)
For a conditional use site plan, the Land Use Commission may:
(1)
approve the site plan as proposed by the applicant if the site plan complies with the requirements of Section 25-5-145 (Evaluation Of Conditional Use Site Plan);
(2)
approve the site plan pending compliance with the requirements of this title or conditions required by the Land Use Commission under Section 25-5-146 (Conditions Of Approval); or
(3)
deny the site plan application.
(C)
The Land Use Commission shall approve a site plan for development in a Hill Country Roadway Corridor if the Land Use Commission determines that the proposed development complies with the requirements of this title.
(D)
The director shall notify the applicant of the Land Use Commission's decision by mail.
Source: Sections 13-1-663(b) and 13-1-664; Ord. 990225-70; Ord. 010607-8; Ord. 031211-11.