If the City approves a preliminary plan and agrees to accept the conveyance of facilities
after construction, the road utility district shall submit construction plans conforming
to the requirements in the Administrative Criteria Manual to the director for review
at least 45 days before construction begins.
(B)
The director shall schedule a meeting between City staff members and road utility
district representatives not later than the 15th day after receipt of the construction
plans to discuss the proposed construction plans and requirements for City approval.
Source: Section 13-1-388.1 and 13-1-389; Ord. 990225-70; Ord. 031211-11.