§ 25-8-183. MODIFICATION OF EROSION CONTROL AND CONSTRUCTION SEQUENCING PLANS.  


Latest version.
  • A City inspector may modify an erosion control plan or construction sequencing plan in the field:

    (1)

    without notice to the permit holder, if the modification is a minor change to upgrade erosion controls or reflect construction progress; and

    (2)

    after two days written notice to the permit holder, if:

    (a)

    the inspector determines that an erosion control or the construction sequencing is inappropriate or inadequate; and

    (b)

    the director has confirmed in writing the inspector's determination.

Source: Section 13-7-14(d); Ord. 990225-70; Ord. 010329-18; Ord. 031211-11; Ord. 20131017-046.