§ 25-9-61. ELIGIBLE PROJECTS.  


Latest version.
  • (A)

    An entity that agrees to construct a water or wastewater main or a facility that on acceptance will become part of the City water and wastewater system may apply to the City for cost participation in a water or wastewater main or a facility if the main or facility is oversized at the request of the City to serve additional property. Cost participation is not permitted for a wastewater main or facility that provides service within the drinking water protection zone.

    (B)

    Under this Section cost participation will apply:

    (1)

    if the improvement is a water main and has a diameter of more than 8 inches;

    (2)

    if the improvement is a wastewater main and has a diameter of more than 8 inches; or

    (3)

    if the improvement is a pump station, reservoir, lift station, force main or wastewater treatment plant.

Source: Section 13-3-15(b), (c), and Table 2; Ord. 990225-70; Ord. 000309-39; Ord. 000406-87; Ord. 031211-11; Ord. 20090820-061; Ord. 20130321-065.