§ 30-2-32. CITY ACTION WITHIN 30 DAYS.  


Latest version.
  • (A)

    The requirements of this section supersede any contrary provisions of this title relating to action by the land use commission or council.

    (B)

    The single office shall schedule an application for preliminary plan or plat approval for consideration by the land use commission or council not later than the 30th day after the application is filed.

    (C)

    The land use commission or council shall act on an application for preliminary plan or plat approval not later than the 30th day after the application is filed.

    (D)

    The council shall act on an appeal of land use commission action on an environmental variance that is associated with a preliminary plan not later than the 30th day after the land use commission action.

Source: City Code Section 25-4-32; Ord. 031211-11; Ord. 031211-42.