§ 1803S.12. Defects and Their Remedies  


Latest version.
  • If any material, either selected for the Work or delivered on the site for use in the Work, shall be deemed by the Director to be unsuitable or not in conformity with the Contract Documents, or the intent thereof, the Owner/Developer and the Contractor shall be notified by the Director in a written notice which identifies and/or describes the unacceptable material. The Owner/Developer, after receipt of written notice from the Director, shall then require the Contractor to immediately remove such material from the jobsite and rebuild or otherwise remedy any effected work so that it shall be in full accordance with the Contract Documents.