Austin |
Standard Specifications Manual |
SERIES 1800 - PRIVATE DEVELOPMENT |
Section 1803S. RESPONSIBILITIES OF THE OWNER/DEVELOPER AND ENGINEER 9-26-12 |
§ 1803S.5. On-Site Pre-construction Meeting
After or in conjunction with the Pre-construction Conference and before the Work begins, an on-site meeting shall be held to review erosion and sedimentation controls. As a minimum the meeting shall include the following individuals:
The Contractor and the Superintendent;
The Inspector assigned to inspect the Work;
A representative from the Department of Watershed Protection and Development Service;
The Consulting Engineer.
The representative from the Department of Watershed Protection and Development Services will be provided with a minimum of 24 hours notice to establish a meeting date and time. If the Department representative does not establish a date and time for the meeting within five days of receiving the notice, construction may proceed.