The Owner/Developer and the Contractor shall warrant the Work for a period of one
year from the date of the Letter of Conditional or Final Acceptance of the completed
Work, unless the period is extended by mutual agreement between the City and the Owner/Developer
or the Contractor, as described below. This warranty shall bind the Owner/Developer
to correct any and all defective materials, substandard work (including utility backfill)
and/or design inadequacies, which may be discovered within the warranty period. The
Owner/Developer shall correct or cause the Contractor to correct at the Contractor's
own expense, such defects no later than 30 calendar days after receipt of a Written
Notice from the Director of such defects. If the Owner/Developer or the Contractor
fail or refuse to correct such defects within the 30 calendar day period or fail to
provide adequate assurances that such work will be completed within a reasonable time
thereafter, the City of Austin may correct, or cause to be corrected, any such defects
at the expense of the Contractor's bond.
If in the opinion of the Director it is desirable to extend the warranty period for
questionable work rather than requiring the Contractor to remove and replace such
work, the warranty period may be lengthened to an extended period of time as agreed
to by the Owner/Developer and/or the Contractor.
var val = document.getElementById('citecontent').innerHTML;
art.dialog.defaults.title = window.location.href;
art.dialog.data('cite', val);
art.dialog.data('homeDemoPath', '/Scripts/plus/artDialog/');
art.dialog.open('/Scripts/plus/artDialog/citeiframe.html');