§ 204S.10. Maintenance  


Latest version.
  • The Contractor shall be required, within the limits of the contract, to maintain the cement treated course in good condition until all work has been completed and accepted. Maintenance shall include immediate repairs of any defects that may occur. This work shall be done by the Contractor at the Contractor's own expense and shall be repeated as often as needed to keep the area continuously intact. Any improper, insufficient or faulty work shall be replaced to the full depth of treatment.

    It is the intent of this specification that the Contractor construct the plan depth of cement treatment in one homogeneous mass. The addition of thin stabilized layers will not be permitted to provide the minimum specified depth.