§ 236S.2. Submittals  


Latest version.
  • The submittal requirements of this specification item may include:

    A.

    A plan describing the condition of each roller proposed for the work, as well as the type of traction (self propelled or drawn), Type of roller, size, weight, tire pressure (if appropriate) and configuration of each individual roller, and

    B.

    The operating speed proposed for each individual roller.