§ 312S.6. Traffic Control Facilities  


Latest version.
  • The Contractor shall arrange the seal coat operation in such a manner as to avoid excessive inconvenience to the public in the seal coat area.

    The Contractor shall notify all abutting property owners along the street prior to initiation of the seal coat operation.

    The Contractor shall have on the project site sufficient barricades, flag-persons and traffic control devices to assure a minimum of inconvenience to traffic around the construction area in conformance with the General Conditions of the Standard Contract Documents. If the Contractor's arrangements are satisfactory to the Engineer or designated representative, the seal coat operation will not be allowed to commence.

    After the seal coat has been applied, the Contractor shall post appropriate warning signs along these streets as directed by the Engineer or designated representative and maintain such signs for 48 hours.