§ 315S.3. Equipment  


Latest version.
  • The equipment for removing the pavement surface shall be a power operated planing machine or grinder with a minimum 2 feet (1.8 meter) cutting width. For detail work and cutting widths less than 2 feet (1.8 meter), equipment with less than 2 feet (1.8 meter) cutting width shall be allowed. The equipment shall be self-propelled with sufficient power, traction and stability to maintain accurate depth of cut and slope. The equipment shall be capable of removing in one pass, asphaltic concrete pavement of a thickness of 1 inch and any required thickness less than 1 inch (25 millimeters) in a minimum 3 foot (0.9 meters) width. Machines capable of removing, in one pass, a depth greater than 1 inch (25 millimeters) will be permitted.

    The grade reference used by the Contractor may be of any type approved by the Engineer or designated representative. Control points, if required by the Drawings, shall be set at intervals not to exceed 50 feet (15 meters). The Contractor shall set the grade reference from the control points. The grade reference shall have sufficient support so that the maximum deflection shall not exceed two millimeters (1/16 inch) between supports.

    The machine shall have a manual system providing for uniformly varying the depth of cut while the machine is in motion, thereby making it possible to cut flush to all inlets, manholes, or other obstructions within the paved area. The speed of the machine shall be variable in order to leave the desired grid pattern as specified in sections 315S.4 and 315S.5.

    The machine shall be equipped with an integral loading and reclaiming means to immediately remove material being cut from the surface of the roadway and discharge the cuttings into a truck, all in one operation. The machine shall be equipped with means to control dust created by the cutting action. Adequate backup equipment (mechanical street sweepers, loaders, water truck, sprayers, brooms etc.) and personnel will also be provided to keep flying dust to a minimum and to insure that all cuttings are removed from the street surface daily. Stockpiling of planed material will not be permitted on the project site.

    Various machines may be permitted to make trial runs to demonstrate the capabilities of that machine and to determine the acceptability of that machine to the Engineer or designated representative. Any machine that is incapable, in the opinion of the Engineer or designated representative, of meeting these requirements will not be permitted.