When included as a pay item in the contract documents, the work performed and materials
furnished as provided by this item and measured in accordance with Article 413S.6, "Measurement", will be paid for at the appropriate unit bid price bid. The unit
bid prices shall include full compensation for cleaning and, if necessary, grooving
and/or sawing the crack/joint; furnishing, hauling and placing primer and backer rod,
if necessary; furnishing, heating, hauling, and placing the crack/joint sealer; all
freight involved and all manipulations, labor, tools, equipment and incidentals necessary
to complete the work.
Payment, when included as a contract pay item, will be made under: