The work performed and materials furnished and measured as provided under "Measurement"
will be paid for at the unit bid price per lineal foot for Diversion as indicated
on the Drawings. The unit bid price shall include: a) full compensation for furnishing,
hauling and placing all materials; b) all labor, tools, seeding, equipment and incidentals
needed to complete the work, c) any repair, replacement and seeding of materials to
maintain the Diversion d) removal and disposal of all materials at the completion
of construction and e) reseeding the areas disturbed by the removal of the temporary
Diversion.
Payment will be made under:
Pay Item No. 621S:
Diversion
Per Lineal Foot.
End
SPECIFIC
CROSS REFERENCE MATERIALS
Specification Item 621S "Diversion (Temporary)"
City of Austin Standard Specifications
Designation
Description
Item No. 130S
Borrow
Item No. 604S
Seeding for Erosion Control
Item No. 606S
Fertilizer
City of Austin Standard Details
Designation
Description
No. 621S-1
Diversion
Texas Department of Transportation: Manual of Testing Procedures
Designation
Description
Tex-103-E
Determination of Moisture Content of Soil Materials
Tex-104-E
Determination of Liquid Limit of Soils
Tex-105-E
Determination of Plastic Limit of Soils
Tex-106-E
Method of Calculating the Plasticity Index of Soils
Tex-114-E
Laboratory Compaction Characteristics and Moisture-Density Relationship of Subgrade
& Embankment Soil
Tex-115-E
Field Method for Determination of In-Place Density of Soils and Base Materials
RELATED
CROSS REFERENCE MATERIALS
Specification Item 621S "Diversion (Temporary)"
City of Austin Land Development Code
Designation
Description
Chapter 25
Drainage
Section 25-7-61
Criteria for Approval of Plats, Construction Plans, And Site Plans
Section 25-7-61 (A) (4)
"temporary and permanent measures to control erosion…"
Section 25-7-65
Fiscal Security
Article 5
Erosion and Sedimentation Control; Overland Flow
Section 25-8-181
Erosion and Sedimentation Control
Section 25-8-182
Development Completion
Section 25-8-183
Modification of Erosion Control and Construction Sequencing Plans
Section 25-8-323
Temporary Storage Areas; Topsoil Protection
Section 25-8-341 (B)
"A cut must be restored and stabilized"
Section 25-8-342 (B)
"A fill must be restored and stabilized"
City of Austin Environmental Criteria Manual
Designation
Description
Section 1.4.0
Erosion and Sedimentation Control Criteria
Section 1.4.1
Introduction
Section 1.4.1.2
Project Management
Section 1.4.2
Temporary Structural Practices
Section 1.4.2.B
Diversion, Interceptor and Perimeter Dikes
City of Austin Standard Specifications
Designation
Description
Item No. 101S
Preparing Right of Way
Item No. 102S
Clearing and Grubbing
Item No. 111S
Excavation
Item No. 132S
Embankment
Item No. 201S
Subgrade Preparation
Item No. 601S
Salvaging and Placing Topsoil
Item No. 605S
Soil Retention Blanket
Item No. 607S
Slope Stabilization
City of Austin Standards (Details)
Standard No.
Description
No. 627S-1
Grass Lined Swale
No. 627S-2
Grass Lined Swale W/ Stone Center
No. 633S-1
Landgrading
Texas Department of Transportation: Standard Specifications for Construction and Maintenance
of Highways, Streets, and Bridges
Designation
Description
Item No. 100
Preparing Right of Way
Item No. 110
Excavation
Item No. 160
Furnishing and Placing Topsoil
Item No. 164
Seeding for Erosion Control
Item No. 166
Fertilizer
Item No. 168
Vegetative Watering
Item No. 169
Soil Retention Blanket
var val = document.getElementById('citecontent').innerHTML;
art.dialog.defaults.title = window.location.href;
art.dialog.data('cite', val);
art.dialog.data('homeDemoPath', '/Scripts/plus/artDialog/');
art.dialog.open('/Scripts/plus/artDialog/citeiframe.html');