§ 643S.1. Description  


Latest version.
  • This item shall consist of a temporary crushed stone dike installed in conjunction with and as part of a diversion dike, interceptor dike or perimeter swale. The purpose of this stone outlet structure is to provide a protected outlet for a diversion dike, interceptor dike or perimeter dike, to provide for diffusion of concentrated flow and to allow the area behind the dike to de-water (Environmental Criteria Manual Section 1.4.2.D). This item shall include removal of the "Stone Outlet Structure" and re-vegetation of the area.

    This specification is applicable for projects or work involving either inch-pound or SI units. Within the text, the inch-pound units are given preference followed by SI units shown within parentheses.