§ 833S.4. Installation  


Latest version.
  • The Contractor will be responsible for installing the pedestrian push-buttons and signs in the field. Drilling wire feed holes and mounting the pedestrian push-button on signal poles will be the Contractor's responsibility.

    All wire feeding through the mast arm pole structure shall be wrapped once with plastic electrical tape and wrapped again with electrical friction tape extending 12 inches (300-mm) on each side of the pole opening for a total of 24 inches (600-mm). Pedestrian push-buttons shall have a common ground wire that is completely isolated and independent from all other ground wires.