§ 4.6.2.8. Energy Final Inspection:  


Latest version.
  • For all new construction projects or additions and remodels where the thermal envelope has been modified, an Energy Final Inspection is required. This inspection is scheduled with the Final Building grouped inspection.

    a)

    Thermal Envelope Leakage: A third party testing report will be provided by a City of Austin approved testing contractor for envelope leakage on all new construction projects. The report must illustrate compliance with the currently adopted Energy Conservation Code.

    b)

    Duct Leakage: A third party testing report will be provided by a City of Austin approved testing contractor for duct leakage on all new construction projects or anytime 100% of the duct work in the structure has been replaced.

    c)

    Ducts located entirely within the building envelope do not require a leakage test.