§ 4.6.2.9. Final Building Inspection
a)
Grouped Final Building Inspection: The Final Building Inspection for new construction, large additions or remodels where the scope of the renovation exceeds 50% of the existing structure shall be scheduled and inspected as a grouped inspection. This includes all required trade inspections, including energy, mechanical and plumbing.
b)
Required documentation at the Building Final Inspection for new construction:
1.
Foundation Letter: See Section 4.6.2 Foundation Inspection;
2.
Subterranean Termite Protection Letter: See Section 4.6.2 Subterranean Termite Protection;
3.
Wallboard Letter: See 4.6.2 Wallboard Inspection;
4.
Energy Reports: See 4.6.2 Energy Finals;
5.
Impervious Coverage Survey (If Applicable): If the impervious coverage for any residential project is within 5% of the maximum amount allowed, then an impervious cover survey is required.