§ 4.6.5.5. Contractor Responsibility  


Latest version.
  • 1.

    The responsible contractor must ensure access to the inspection site and equipment for inspection. The responsible contractor or a representative of the homeowner who is 18 years old or older must be present for the inspection.

    2.

    The responsible contractor shall submit a completed "Replacement Change Out Completeness Form" to the City within five days of equipment installation for work completed under this section for which no inspections are performed by a City Inspector attesting that the work performed meets all Code requirements. The responsible contractor shall submit the form to the address shown in this section.

    3.

    The responsible contractor is responsible for ensuring that all associated permits are secured and that all fees are paid in full before inspections can be scheduled.

    4.

    The City of Austin will accept the "Replacement Change Out Completeness Form" by either method of delivery listed below:

    a)

    Electronic mail to: building.inspections@austintexas.gov

    b)

    Mail or Hand Delivery to:

    City of Austin, Building Inspections
    505 Barton Springs Road, Suite 300
    Austin, Texas 78704