§ 5.2.5. ELECTRICAL UTILITY SERVICE REQUEST  


Latest version.
  • This rule is promulgated to administer and implement requirements for service by the City of Austin Electric Utility.

    A.

    Basic

    1.

    All electric plans will include the following: Legal address of the lot as assigned by the Transportation and Public Services Department; volume and page of all recorded easements; recorded plat; contour map (if required by site plan approval process); tree survey (if required by site plan approval process).

    2.

    Determination of aid to construction fee requirements

    a.

    Voltage

    b.

    Number of phases

    c.

    Wire size at service entrance

    B.

    Residential and Tract Development

    1.

    Reproducible preliminary or final subdivision plat, if a recorded plat is not available.

    2.

    Utility plans to include: paving, drainage, water, wastewater, gas and oil pipeline.

    3.

    Erosion and sedimentation control plans

    C.

    Commercial and Industrial

    1.

    Load analysis for individual structures

    2.

    One (1) line electrical diagram

    3.

    Switchgear approval drawings

    4.

    On site utility plan and profiles

    5.

    The date permanent service is required

    All plans submitted shall include: the seal of the engineer responsible for the plans, the signature of said engineer, the date of the plan revision, the scale of the drawings and notation of the north direction.