§ 14-11-166. PROJECT COORDINATION.  


Latest version.
  • (A)

    At the director's request, an owner shall coordinate excavation or facility installation plans with other excavation and installation and the department's paving and utility program in the right-of-way.

    (B)

    An owner shall follow facilities replacement schedules that avoid construction conflicts and prevent delays of proposed city utility and street projects.

    (C)

    The owner of a permitted facility that is installed in a right-of-way shall identify the facility in a manner approved by the director.

    (D)

    The director shall prescribe rules for the identification of facilities in the right-of-way.

Source: Ord. No. 20170817-045 , Pt. 2, 8-17-17.