§ 30-1-357. FINAL INSPECTION.


Latest version.
  • (A)

    Not later than the fourth day after the owner gives written notice that work under a subdivision construction plan is substantially complete, the single office shall:

    (1)

    review the work; and

    (2)

    prepare a report identifying work that does not comply with the construction plans and work that must be performed before the accountable official issues a final acceptance letter.

    (B)

    When the owner finishes the work listed in the report issued under Subsection (A), the single office shall modify the report to reflect completion of the required work.

Source: City Code Section 25-1-313; Ord. 031211-11; Ord. 031211-42.