§ 30-1-356. SUBSTANTIAL COMPLETION NOTICE.
Latest version.
(A)
Approximately 10 days before work under the subdivision construction plans is finished, the owner shall notify the single office in writing that the work is substantially complete and shall request a report listing the work to be completed.
(B)
On the day that the owner provides notice under Subsection (A), the consulting engineer shall submit a construction summary report to the single office.
Source: City Code Section 25-1-312; Ord. 031211-11; Ord. 031211-42.