§ 1806S.1. Substantial Completion
Substantial Completion shall be defined as the date when, in the opinion of the Owner/Developer or the Consulting Engineer, the Work is sufficiently complete in accordance with the Contract Documents that the Owner/Developer can occupy or utilize the Work for its intended purpose. The Owner/Developer should also at this time require the Consulting Engineer to prepare and forward a Construction Summary Report to the Director. The Construction Summary Report is required prior to the preparation of the City of Austin Final Acceptance Letter.
This specification is applicable for projects or work involving either inch-pound or SI units. Within the text, the inch-pound units are given preference followed by SI units shown within parentheses.