§ 1806S.2. Final Inspection  


Latest version.
  • Within four (4) working days of the date when the Owner/Developer presented the Director with a Written Notice that the Work was substantially completed, the Inspector will schedule and conduct a review of the Work and will prepare a Report of the Private Development Inspection (punchlist) for the Owner/Developer with copies provided for the Consulting Engineer, the Contractor and the Construction Supervisor. This form will include:

    Any remaining items discovered not in compliance with Construction Documents; or other items required for the issuance of the Final Acceptance Letter.

    Work that is shown on the Contract Documents as "Temporary Construction" will not be accepted by the City of Austin unless prior approval for the Work has been previously secured from the Department of Watershed Protection and Development Services.

    If the sole remaining unfinished item on the Report of the Private Development Inspection is the re-establishment of vegetation, the Owner/Developer may desire to execute a Re-vegetation Letter to ensure completion of this item. The Re-vegetation Letter will retain the fiscal posting for erosion/sedimentation control and re-vegetation for the Work. This Work must be accomplished within 120 days of the date of Conditional Acceptance of the Project.

    The Construction Inspection Supervisor will review and sign the Report of Private Development Inspection when all items entered are completed or satisfied by the above described Re-vegetation Letter. A meeting for the Final Inspection may then be scheduled by the Inspector at a time convenient to the Owner/Developer and the Director, as outlined in Section 1806S.3.

    The issuance of the Report of Private Development Inspection shall not excuse the Owner/Developer from requiring the Contractor to perform all the work required by the Contract Documents regardless of the time of discovery.