§ 510.5. Payment


Latest version.
  • Payment for pipe, measured as prescribed above, will be made at the unit price bid per linear foot for the various sizes of pipe, of the materials and type indicated, unless unstable material is encountered or trench excavation and backfill is bid as a separate item.

    The concrete seal, foundation rock or coarse aggregate when used as directed in unstable material will be paid for at the unit price bid per cubic yard, which shall be full payment for all excavation and removal of unsuitable material and furnishing, placing and compacting the foundation rock, coarse aggregate or other approved material all complete in place.

    Excavation and backfill, when included as a separate pay item, will be paid for by Pay Item No. 510-E or 510-F.

    No separate payment will be made for dewatering a trench with ground water inflow of less than the baseline rate of 350 gpm of sustained flow as described above. Dewatering of those trenches shall be included in the contract unit price of the Pipe pay item. Payment for dewatering a trench with ground water inflow exceeding 350 gpm of sustained flow shall be agreed by change order. Dewatering of bore pits shall be included in the contract unit price for Bore Entry Pit or Exit Pit regardless of inflow rate or volume unless specified otherwise in the bid item for Bore Entry Pit or Exit Pit.

    (1)

    Pipe

    Payment for pipe, measured as prescribed above, will be made at the unit price bid per linear foot complete-in-place as designed and represented in the Drawings and other Contract documents. Restrained joint pipe meeting the requirements of Standard Products List WW-27F will be paid for separately at the unit price bid per linear foot. Unless otherwise provided herein, as separate pay item(s), the bid price per linear foot of pipe shall include the following:

    a.

    clearing

    b.

    constructing any necessary embankment

    c.

    excavation

    d.

    disposal of surplus or unusable excavated material

    e.

    furnishing, hauling and placing pipe

    f.

    field constructed joints, collars, temporary plugs, caps or bulkheads

    g.

    all necessary lugs, rods or braces

    h.

    pipe coatings and protection

    i.

    connections to existing systems or structures, concrete blocking and thrust blocks and restrained joints

    j.

    preparing, shaping, pumping for dewatering, and shoring of trenches

    k.

    bedding materials

    l.

    backfill materials

    m.

    hauling, placing and preparing bedding materials

    n.

    particle migration measures

    o.

    hauling, moving, placing and compacting backfill materials

    p.

    temporary and permanent pavement repairs and maintenance

    q.

    temporary removal and replacement of pavement, curb, drainage structures, driveways, sidewalks and any other improvements damaged or removed during construction

    r.

    cleanup

    s.

    vertical stack on deep wastewater services

    t.

    all other incidentals necessary to complete the pipe installation as indicated.

    u.

    pipe joint restraint devices, where specified or allowed, meeting Standard Products List WW-27A or WW-27G.

    No separate payment will be made for thrust restraint measures.

    Steel cylinder concrete pipe fittings and welded steel pipe fittings will not be paid for separately. These will be included in the unit price bid for the bid item Pipe.

    (2)

    Concrete Cradles and Seals

    When called for in the Bid, concrete cradles and seals will be paid for at the unit Contract price bid per linear foot for the size of pipe specified, complete in place.

    (3)

    Concrete Retards

    When called for in the Bid, Concrete retards will be paid under Item No. 593S, Concrete Retards."

    (4)

    Boring or Jacking.

    When called for in the Bid, boring or jacking will be paid under Item 501S, "Jacking or Boring Pipe.

    (5)

    Wet Connections to Potable or Reclaimed Water Mains

    When called for in the bid, wet connections will be paid at the unit price bid per each, complete in place, according to the size of the main that is in service and shall be full compensation for all Work required to make the connection and place the pipe in service. (See subsection 510.3 'Construction Methods' part (24) (b) 'Wet Connections to Existing Water System').

    (6)

    Fittings

    Ductile iron fittings, furnished in accordance with these specifications, will be paid for at the unit price bid per ton, complete in place, according to the schedule of weights in Standard Products List WW-27C. Bolts, glands, and gaskets will not be paid for separately and shall be included in the contract unit price for fittings.

    (7)

    Concrete Trench Cap and Encasement

    Where the distance between the top of the concrete encasement and the top of the trench cap is less than 36 inches, the concrete cap and encasement shall be poured as one unit and paid for under this bid item at the Contract price bid per linear foot. When the distance above is greater than 36 inches or when the trench cap is placed separately, the trench cap shall be paid for as a separate item, per linear foot, complete in place.

    (8)

    Cement-Stabilized Backfill

    Cement-stabilized backfill will be paid for at the unit price bid per linear foot and shall be full payment to the Contractor for furnishing and installing the required material, mixed, placed and cured complete in place.

    (9)

    Concrete Encasement

    When called for in the Bid, Concrete Pipe Encasement will be paid under Item No. 505S, "Encasement and Encasement Pipe".

    (10)

    Pressure Taps

    Pressure taps will be paid for at the unit price bid, complete in place, according to the size tap made and the size main tapped and shall be full payment for furnishing all necessary materials, including tapping sleeve and valve, making the tap, testing and placing the connection in service.

    (11)

    Excavation Safety Systems

    When called for in Bid, Trench Safety Systems shall conform to Item No. 509S, "Excavation Safety Systems."

    (12)

    Connecting a New Water, Wastewater, or Reclaimed Water Service to an existing, comparable type of private service will be paid for at the unit price bid, complete in place, according to the size of new service and size of existing private service, and shall be full payment for furnishing and installing all necessary materials, such as cleanouts, pipe, couplings, and fittings, and including excavation and backfill.

    (13)

    Video Inspection

    Video Inspection of Newly Installed Box Culverts and Storm Drain Pipe will be paid for at the unit price bid per linear foot and shall be full payment for all labor, equipment, and materials required for video inspection per this specification, including all submittals of CD/DVD as required.

    (14)

    Jumper Hose

    Jumper Hose will be paid at the unit bid price, complete and in place, including installation and removal of all materials necessary to provide a fully functional jumper hose. This item shall also include adequate protection for the jumper hose within vehicular traffic areas.

    Source: Rule No. R161-17.05 , 5-31-2017.

    Payment, when included as a Contract pay item, will be made under one of the following:

    Pay Item No. 510-AR___Dia.: Pipe, ___ Dia. ___ Type (all depths), including Excavation and Backfill Per Linear Foot.
    Pay Item No. 510-ARRJ___Dia.: Factory Restrained Joint Pipe, ___ Dia., Class ___ Ductile Iron, (all depths) including Excavation and Backfill Per Linear Foot.
    Pay Item No. 510-BR___×___Dia.: Connecting New ___ Service to Existing Private Service (___ Dia. New Service to ___ Dia. Private Service) Per Each.
    Pay Item No. 510-CR: Pipe Excavation, ___ Ft. Width Per Linear Foot.
    Pay Item No. 510-DR: Pipe Trench Backfill, ___ Ft. Width Per Linear Foot.
    Pay Item No. 510-ER: Concrete Seal or Cradle, ___ Dia. Pipe Per Linear Foot.
    Pay Item No. 510-FR: Concrete Trench Cap, ___ Ft. Width Per Linear Foot.
    Pay Item No. 510-GR: Concrete Cap and Encasement, ___ Dia. Pipe Per Linear Foot.
    Pay Item No. 510-HR: Cement Stabilized Backfill, ___ Dia. Pipe Per Linear Foot.
    Pay Item No. 510-IR: ___ × ___ Dia.: Pressure Taps, ___ Dia. × ___ Dia. Per Each.
    Pay Item No. 510-JR: ___ × ___ Dia.: Wet Connections, ___ Dia. × ___ Dia. Per Each.
    Pay Item No. 510-KR: Ductile Iron Fittings Per Ton.
    Pay Item No. 510-ASD___Dia.: Pipe, ___ Dia. (all depths), including excavation and backfill Per Linear Foot.
    Pay Item No. 510-CSD: Pipe Excavation, ___ Ft. Width Per Linear Foot.
    Pay Item No. 510-DSD: Pipe Trench Backfill, ___ Ft. Width Per Linear Foot.
    Pay Item No. 510-ESD: Concrete Seal or Cradle, ___ Dia. Pipe Per Linear Foot.
    Pay Item No. 510-FSD: Concrete Trench Cap, ___ Ft. Width Per Linear Foot.
    Pay Item No. 510-GSD: Concrete Cap and Encasement, ___ Dia. Pipe Per Linear Foot.
    Pay Item No. 510-HSD: Cement Stabilized Backfill, ___ Dia. Pipe Per Linear Foot.
    Pay Item No. 510-AW___ Dia.: Pipe, ___ Dia. ___ Type (all depths), including excavation and backfill Per Linear Foot
    Pay Item No. 510-AWRJ___ Dia.: Factory Restrained Joint Pipe, ___ Dia., Class Ductile Iron, (all depths) including Excavation and Backfill Per Linear Foot.
    Pay Item No. 510-BW___ × ___ Dia.: Connecting New ___ Service to Existing Private Service (___ Dia. New Service to ___ Dia. Private Service) Per Each.
    Pay Item No. 510-CW: Pipe Excavation, ___ Ft. Width Per Linear Foot.
    Pay Item No. 510-DW: Pipe Trench Backfill, ___ Ft. Width Per Linear Foot.
    Pay Item No. 510-EW: Concrete Seal or Cradle, ___ Dia. Pipe Per Linear Foot.
    Pay Item No. 510-FW: Concrete Trench Cap, ___ Ft. Width Per Linear Foot.
    Pay Item No. 510-GW: Concrete Cap and Encasement, ___ Dia. Pipe Per Linear Foot.
    Pay Item No. 510-HW: Cement Stabilized Backfill, ___ Dia. Pipe Per Linear Foot.
    Pay Item No. 510-IW:___ × ___ Dia.: Pressure Taps, ___ Dia. × ___ Dia. Per Each.
    Pay Item No. 510-JW: ___ × ___ Dia.: Wet Connections, ___ Dia. × ___ Dia. Per Each.
    Pay Item No. 510-KW: Ductile Iron Fittings Per Ton.
    Pay Item No. 510-AWW: ___ Dia.: Pipe, ___ Dia. ___ Type (all depths), including Excavation and Backfill Per Linear Foot.
    Pay Item No. 510-AWWRJ___ Dia.: Factory Restrained Joint Pipe, ___ Dia., Class ductile Iron, (all depths) including Excavation and Backfill Per Linear Foot.
    Pay Item No. 510-BWW___ × ___ Dia.: Connecting New ___ Service to Existing Private Service (___ Dia. New Service to ___ Dia. Private Service) Per Each.
    Pay Item No. 510-CWW: Pipe Excavation, ___ Ft. Width Per Linear Foot.
    Pay Item No. 510-DWW: Pipe Trench Backfill, ___ Ft. Width Per Linear Foot.
    Pay Item No. 510-EWW: Concrete Seal or Cradle, ___ Dia. Pipe Per Linear Foot.
    Pay Item No. 510-FWW: Concrete Trench Cap, ___ Ft. Width Per Linear Foot.
    Pay Item No. 510-GWW: Concrete Cap and Encasement, ___ Dia. Pipe Per Linear Foot.
    Pay Item No. 510-HWW: Cement Stabilized Backfill, ___ Dia. Pipe Per Linear Foot.
    Pay Item No. 510-KWW: Ductile Iron Fittings Per Ton.
    Pay Item No. 510-VIDEO Video Inspection of Newly Installed Box Culverts and Storm Drain Pipe Per Linear Foot.
    Pay Item No. 510-JH 2-inch Jumper Hose Per Linear Foot.

     

    An "R" after the pay item indicates the use for reclaimed water.

    An "SD" after the pay item indicates the use for storm drain.

    A "W" after the pay item indicates the use for water.

    A "WW" after the pay item indicates the use for wastewater.

    Source: Rule No. R161-17.05 , 5-31-2017.

    End

    Applicable References:

    Standard Specifications Manual: Item Nos. Ref: 102S, 210S, 402S, 403, 501S, 505S, 506, 507S, 509S, 593S, 601S, 604S

    Standards Manual: Standard Detail Nos. 510S-1, (520 - series).

    Design Criteria Manuals: Utilities Criteria Manual, Section 5.